Many power projects are behind schedule, increasing power shortage pressure

VCN- Power projects that are behind schedule or have been delayed for many years have been identified as one of the main reasons for the danger of upcoming power shortages. Deciding to remove this "bottleneck" is the most critical solution to reduce the risk of power shortage in Vietnam in the medium term.
tin nhap 20190726155306 Measures needed for delayed thermal power projects
tin nhap 20190726155306 Many loss-making projects have reduced financial pressure by hundreds of billions VND
tin nhap 20190726155306 FDI poured into industrial zones in 6 months
tin nhap 20190726155306
Long Phu 1 thermoelectricity plant is a typical slow power projects. Photo: N.Thanh

Power shortage in 2021

A report of Department of Electricity and Renewable Energy (Ministry of Industry and Trade) showed that to meet electricity demand with an average growth rate of 8.6 percent/year according to the basic plan in Electricity Planning VII adjusted (the output of electricity needed to be supplemented on an average of 26.5 billion kWh/year), each year, the power source capacity needs to be supplemented with at least 4,500-5,000 MW of thermal power source or from 14,000-16,000 MW if using the renewable sources (due to low capacity utilisation of renewable energy sources, only from 1,500-2,000h/year).

Phuong Hoang Kim - Director of Department of Electricity and Renewable Energy said, in 2020, basically, electricity demand for socio-economic development will be met. However, supply of electricity continues to have some potential risks, which may face the risk of power shortage in extreme situations such as demand is higher than supply, water flow to hydroelectric reservoirs is poor and continued shortage of coal and gas for electricity production.

In 2021-2025, according to the Department of Electricity and Renewable Energy, the whole system will lack electricity (although it has to mobilise maximum power sources, including oil sources). Specifically, the shortage output in 2021 is about 6.6 billion kWh; by 2022, it will increase to about 11.8 billion kWh; 2023 can be up to 15 billion kWh (equivalent to ~ 5 percent of demand). In the years 2024-2025, the shortage will decrease gradually after supplementing the power source from the Block B, Blue Whale.

47 power projects "delay"

Many big power source projects are behind schedule, especially BOT power sources and coal-fired thermal power projects are identified as the key causes leading to the risk of power shortage mentioned above.

According to the adjusted VII Electricity Plan, the total capacity of power sources expected to be put into operation in 2016-2020 is 21,650 MW. Currently, power source projects are implemented in three forms of investment, including projects by State-owned corporations including Electricity of Vietnam (EVN), Vietnam Oil and Gas Group (PVN), Group Vietnam Coal-Mineral Industry (TKV) is the investor; investment projects in the form of Build-Operate-Transfer (BOT); and investment projects in the form of independent electricity projects (IPP).

Through further analysis of power projects, Phuong Hoang Kim pointed out that the progress of implementing 62 projects with large capacity of more than 200 MW, 15 projects reached progress, the remaining 47 projects were behind schedule or have not determined the progress compared to the schedule stated in the VIIth Electricity Plan adjusted. For example, in 2016-2030, EVN was assigned to invest in 24 projects (including Bac Ai hydropower project) with a total capacity of 15,215 MW, with a target that in 2016-2020 it would have completed 14 projects with a total capacity of 7,185 MW. Out of the 24 projects, nine have generated electricity, six are scheduled to be on schedule and nine are behind schedule. Notably, PVN was assigned to be the investor of eight key power source projects with total capacity of 11,400 MW. In the period 2016-2020 there are three projects and 2021-2025 has five projects. So far, all eight projects have difficulties and problems and cannot be completed according to the schedule in the Electricity Plan VII adjusted.

Regarding this issue, Deputy Minister of Industry and Trade Hoang Quoc Vuong added that the characteristics of energy projects are large-scale, most of thermal power projects have a total investment of more than 2 billion USD, construction time is relatively long with thousands of complicated issues. Therefore, the investor cannot find a contractor with the ability to lead to the possibility of lasting many years. In addition, policy changes in guaranteeing projects, even for a strong financial group like PVN without Government guarantees, will face difficulties in capital issues. In the past, when there was a Government guarantee of only one year to arrange capital, there is no more now, it will certainly be longer. "Of the 62 electricity projects implemented, only 15 projects have reached the schedule so far, 47 projects are slow, there are 3-4 projects behind schedule. If there is no remedy, this will be big difficulties in the coming time," Deputy Minister Vuong said.

Determine the progress of the project

Minister of Industry and Trade Tran Tuan Anh assessed that the slow progress of electricity projects leads to immediate risks including both subjective and objective reasons. In subjective reasons, there are difficult issues due to overlapping regulations and procedures but there are also problems that can be solved. Anh asked the Department of Electricity and Renewable Energy and other relevant units to speed up the progress of projects, working with the highest sense of responsibility and review sanctions and legal regulations for investors whose projects are behind schedule.

Notably, with BOT power projects, Anh raised the issue of having an investor receive the project and then find a way to sell the project. Take the Long Phu 2 project of Tata (India) in Soc Trang as an example, Minister Tran Tuan Anh said they seek to sell the project to other investors. He requested the Department of Electricity and Renewable Energy to re-understand the mechanism and legal mechanism to avoid assigning projects to "irresponsible investors", causing great frustration for the central Government as well as local authorities.

Deputy Minister Vuong said to solve the lack of electricity, it is necessary to accelerate the implementation of renewable energy projects by the time of implementing these projects faster than thermal power. In the medium term, it is necessary to accelerate the progress of ongoing projects. Accordingly, a monthly meeting must be held once, three months to set up an inspection team to the works once. Projects that have simple problems that can be handled sooner need to be accelerated. In the long term, it is necessary to change the way of making the electricity diagram VIII.

It is also important to emphasise the responsibilities of some local leaders due to the lack of drastic direction for projects in the Electricity Plan VII adjusted, leading to a break in the structure of the planning, Minister Tran Tuan Anh stated clearly for the Electricity Planning VIII, the units under the Ministry are required to accelerate the completion, in which, the method of implementing and updating the actual situation, paying attention to the source structure and issues related to technology, the legal framework in the future.

By Duc Quang/ Huu Tuc

Related News

Creating a breakthrough in disbursement of public investment capital

Creating a breakthrough in disbursement of public investment capital

VCN – In order for the public investment disbursement rate in 2023 to reach the set target, from the first months of the year, many fundamental and feasible solutions have been taken to remove problems in this work.
Localities propose to remove bottlenecks in disbursement of public investment

Localities propose to remove bottlenecks in disbursement of public investment

VCN – To promote the disbursement of public investment, some localities proposed to complete documents of three national target programs urgently and to solve soon problems related to procedures for disbursement of public investment, including implementation planning of projects.
Urgently disbursing public investment at beginning of the year

Urgently disbursing public investment at beginning of the year

VCN – The disbursement rate of public investment from the State budget in 2022 has not reached as expected. This requires ministries, sectors and localities to provide solutions and expedite this work, disburse public investment into projects for projects' economic development.
Outward investment of SOEs sees positive changes

Outward investment of SOEs sees positive changes

VCN - The outward investment of state-owned enterprises (SOEs) is not entirely directly invested by the parent company, but mainly through subsidiaries. In 2021, many outward investment projects of SOEs and enterprises with state capital recorded a surge in revenue and profits year-on-year besides loss-making investment projects. To improve efficiency of investment, the Government will restructure outward investment activities.

Latest News

Saigontex 2023 attracts over 1,300 domestic, foreign businesses

Saigontex 2023 attracts over 1,300 domestic, foreign businesses

More than 1,300 businesses from 21 countries and territories are participating in the Vietnam Textile & Garment Industry Expo (Saigontex) 2023, the leading exhibition of the industry in Southeast Asia, which opened in Ho Chi Minh City on April 5.
Mong Cai international border gate sees strong recovery

Mong Cai international border gate sees strong recovery

The Mong Cai international border gate in the northern province of Quang Ninh has become vibrant as before the pandemic, showing a positive sign in the economic recovery of Mong Cai city in particular and Quang Ninh province in general.
Vietnam a potential market for French businesses, investors: experts

Vietnam a potential market for French businesses, investors: experts

French businesses should innovate their approach, enhance their understanding of culture and language, and make changes to adapt to Vietnam's transitioning economy in order to expand their market share and boost investment in the Southeast Asian nation, said Dr. Jean-Philippe Eglinger, the founder of the Viet Phap Strategies.
Import and export turnover across Cao Bang prospers but still exists difficulties

Import and export turnover across Cao Bang prospers but still exists difficulties

VCN – After China resumes trade, Cao Bang province's import and export activities see remarkable prosperity.

More News

Cashew industry strives to "get on the shelves of world supermarkets"

Cashew industry strives to "get on the shelves of world supermarkets"

VCN - Although holding the number one position in the world in exporting cashew kernels for many years, the position of Vietnam's cashew industry in the world cashew value chain is very small because it mainly exports kernels with preliminary treatment.
HCM City’s industrial production index down 0.9% in Q1

HCM City’s industrial production index down 0.9% in Q1

Ho Chi Minh City’s Index of Industrial Production (IIP) in the first quarter of 2023 declined by 0.9% compared to the same period last year, the municipal Department of Industry and Trade reported at a press conference on April 3.
Fisheries exports estimated at 1.85 billion USD in Q1

Fisheries exports estimated at 1.85 billion USD in Q1

Fisheries export value was estimated at 1.85 billion USD in the first quarter (Q1) of this year, a fall of 27% compared to the same period last year due to lower consumption and import demand under the impacts of inflation and economic recession, according to the Vietnam Association of Seafood Exporters and Producers (VASEP).
Quang Ninh aims to attract quality FDI inflows

Quang Ninh aims to attract quality FDI inflows

The northern coastal province of Quang Ninh has strengthened measures to attract quality foreign direct investment (FDI) inflows, especially from big names in the processing-manufacturing industry.
Exports face many difficulties

Exports face many difficulties

VCN - In the first months of 2023, the absence of export orders plus the downward trend in commodity prices have slowed down trade activities.
Manufacturing enterprises increase their competitiveness thanks to digital transformation

Manufacturing enterprises increase their competitiveness thanks to digital transformation

VCN - Overcoming difficulties in 2023 requires manufacturing enterprises to self-improve and innovate. Digital technology is one of the effective solutions to help manufacturing businesses grow and compete.
32nd Việt Nam Expo promises to boost business linkages

32nd Việt Nam Expo promises to boost business linkages

The 32nd Việt Nam International Exhibition (Vietnam Expo) will take place in Hà Nội from April 5-8 with the participation of more than 500 domestic and foreign enterprieses, the event’s organisers have announced.
Prevention of price risks before news that Indonesia increases rice imports in reserve

Prevention of price risks before news that Indonesia increases rice imports in reserve

VCN - In response to demand signals from key markets such as Indonesia and the Philippines, the Import-Export Department (Ministry of Industry and Trade) suggested that rice exporters actively monitor the market situation and fully assess the opportunities as well as risks to build a trading plan.
Japanese investors highly appreciate Vietnamese property market

Japanese investors highly appreciate Vietnamese property market

Representatives from around 180 Japanese businesses and investors on April 1 attended a Tokyo workshop on Vietnamese real estate, during which many of them highly appreciated the potential of Vietnam’s property market.
Read More

Your care

The system has not recorded your reading habits.

Please Login/Register so that the system can provide articles according to your reading needs.

Latest Most read
Saigontex 2023 attracts over 1,300 domestic, foreign businesses

Saigontex 2023 attracts over 1,300 domestic, foreign businesses

More than 1,300 businesses from 21 countries and territories are participating in the Vietnam Textile & Garment Industry Expo (Saigontex) 2023, the leading exhibition of the industry in Southeast Asia, which opened in Ho Chi Minh City on April 5.
Mong Cai international border gate sees strong recovery

Mong Cai international border gate sees strong recovery

The Mong Cai international border gate in the northern province of Quang Ninh has become vibrant as before the pandemic, showing a positive sign in the economic recovery of Mong Cai city in particular and Quang Ninh province in general.
Vietnam a potential market for French businesses, investors: experts

Vietnam a potential market for French businesses, investors: experts

French businesses should innovate their approach, enhance their understanding of culture and language, and make changes to adapt to Vietnam's transitioning economy in order to expand their market share and boost investment in the Southeast Asian nation, said Dr. Jean-Philippe Eglinger, the founder of the Viet Phap Strategies.
Import and export turnover across Cao Bang prospers but still exists difficulties

Import and export turnover across Cao Bang prospers but still exists difficulties

VCN – After China resumes trade, Cao Bang province's import and export activities see remarkable prosperity.
Cashew industry strives to "get on the shelves of world supermarkets"

Cashew industry strives to "get on the shelves of world supermarkets"

VCN - Looking back to 2022, while the export turnover of the cashew industry reached US $ 3.08 billion, the import turnover of raw cashews consumed US $ 2.678 billion.
Mobile Version