Measures needed for delayed thermal power projects

VCN - Many thermal power plant projects of Vietnam Oil and Gas Group (PVN) are falling into stagnation and slow progress. This issue requires specific mechanisms and solutions.  
tin nhap 20190719151108 Driving away the challenges in coal thermal power development
tin nhap 20190719151108 Vietnam’s coal imports grow despite large reserves
tin nhap 20190719151108 Basing on the coal power, difficulty of ensuring energy security
tin nhap 20190719151108
It is expected that the Thai Binh 2 thermal power station will complete unit 1 in June, 2020 and unit 2 in October, 2020. Photo: Nguyen Thanh.

Lack of capital

Thai Binh 2 thermal power plant (Thai Binh) and Song Hau 1 thermal power plant project (Hau Giang) are two projects by PVN that are progressing slowly. Thai Binh 2 thermal power plant project has total investment (adjusted for the second time) of over VND 41 trillion, and so far, the overall progress has reached more than 84%. In particular, most of the main construction items of the project have been completed and are in the finishing stage. According to the expected schedule, the project will complete unit 1 in June, 2020 and unit 2 in October, 2020.

The cause of slow progress was indicated by the contractor of Vietnam Oil and Gas Construction Joint Stock Corporation (PVC) in the process of implementing the project, there were a number of violations which were being reviewed and dealt with by the authorities.

Specifically, the incorrect use of more than VND 1,100 billion led to consequences in terms of costs, progress and legal issues affecting resources in project implementation.

The project's legal documents and procedures have some unsecured issues, so there are items that can be completed but cannot be finalized, including psychological factors of the officials sent to "rescue" this project. In addition, because the project’s progress is prolonged, there are many difficulties and risks that arise, such as the warranties of the machinery and equipment expiring.

"If it is not possible to operate, it is not known which source to replace 1,200 MW of the project's capacity to face the danger of electricity shortage nationwide after 2020. Along with that, if the project does not operate, all investment costs cannot be recovered as there is no source to repay the project loan. Therefore, it is necessary to have a specific mechanism to resolve the capital for this plant to go into operation soon,” said Mr. Dinh Van Son, Member of PVN's Board of Members.

The Song Hau thermal power plant project 1 is also facing difficulties. The project has a total after-tax investment of over VND 43 trillion. The cumulative progress of the project is about 74%, about 24.7 months late compared to the schedule under the signed General Contractor Contract (EPC). It is expected that Song Hau 1 thermal power plant project will complete unit 1 in May 2021 and unit 2 in September 2021.

PVN stated that currently, the project is being applied by the Government with a special mechanism, allowing to implement the form of price adjustment contract for the construction, installation and processing according to Decision No. 2414/QD-TTg dated 11/12/2013 on adjusting the list of schedules of some electricity projects and stipulating some specific mechanisms and policies to invest in urgent power projects in the period 2013-2020.

However, due to the nature and characteristics of the project's work, the plan to adjust the price of EPC contracts does not have specific regulations and guidelines of the competent authorities. Both investors and general contractors have no experience in implementing EPC contracts in the form of price adjustment, so the parties have faced many problems during the implementation process. This leads to the fact that the payment has not met the construction schedule, affecting the payment cash flow for the general contractor and subcontractors to implement the work.

Progress not yet verified

The Long Phu 1 thermal power plant project (Soc Trang) of PVN is also facing slow progress.

The Long Phu 1 thermal power plant project has a capacity of 1,200MW, with an investment of more than VND29.5 trillion. Under the initial plan, Unit 1 was to be completed by the end of 2018 (after 45 months of implementation) and Unit 2 on the first day of 2019 (after 49 months of deployment). However, so far, the project has only completed 77.56% of the plan.

Regarding the cause of slow progress, Mr. Nguyen Doan Toan, Head of Management Unit of Long Phu 1 Thermal Power Plant Project, said that it was mainly due to Power Machines contractor (PM-Russia) imposing a direct embargo against the US government from January 26, 2018. From the time of PM’s embargo, the procurement of goods, import equipment and capital arrangement for projects under the scope of work of PM have seen almost no specific progress.

The project has not been able to determine the feasible progress since the PM contractor did not continue to implement the EPC Contract (design contract, supply of technology equipment and construction works) due to the effects of the embargo. Stopping construction for a long period may lead to malfunctions and unsafe work, causing damage and corrosion of materials and equipment of the project.

The total investment of the project has been established since 2010 and at the present time it is no longer suitable, so there is not enough financial resource to pay for the contractor. Currently, PVN has submitted the adjusted total investment of the project to the Ministry of Industry and Trade for appraisal. However, the appraisal of ministries and agencies has been slow, affecting the implementation of the project. Along with that, the construction and payment activities of the project faces difficulties due to foreign banks, as well as Vietnamese commercial banks, refusing to implement financial transactions related to PM contractors.

In the direction of solving the difficulties and obstacles of the above-mentioned thermal power projects, PVN has now proposed solutions to the Government, ministries and functional agencies. Specifically, for Thai Binh 2 thermal power plant project, PVN proposed to the Government while the additional loan has not been arranged, it approve the policy for PVN to use equity for the project provided that it not exceed the total adjusted investment. When the additional loan is arranged, the equity will be returned.

Currently, the disbursement value of the project is about VND 32.9 trillion. If it is not resolved promptly, the project will continue to be delayed.

For Long Phu 1 Thermal Power Plant Project, PVN proposed to the Government to consider setting up a special working group chaired by the Ministry of Industry and Trade and the Commission for the Managenment of State Capital at Enterprises, the members are leaders of ministries and branches related to Long Phu 1 Thermal Power Plant Project to direct, guide and support PVN in solving difficulties and problems of the project.

tin nhap 20190719151108 Block low-tech coal-fired power projects: Are technical barriers feasible?

In particular, PVN petitioned the Government to allow PVN to use its equity to exceed 30% of the total value of the proposed investment to continue to implement unfinished construction items of the project to technical stops and implementation of maintenance and preservation of materials, equipment items to ensure the quality of the work.

By Thanh Nguyen/ Quynh Lan

Related News

Creating a breakthrough in disbursement of public investment capital

Creating a breakthrough in disbursement of public investment capital

VCN – In order for the public investment disbursement rate in 2023 to reach the set target, from the first months of the year, many fundamental and feasible solutions have been taken to remove problems in this work.
Localities propose to remove bottlenecks in disbursement of public investment

Localities propose to remove bottlenecks in disbursement of public investment

VCN – To promote the disbursement of public investment, some localities proposed to complete documents of three national target programs urgently and to solve soon problems related to procedures for disbursement of public investment, including implementation planning of projects.
Urgently disbursing public investment at beginning of the year

Urgently disbursing public investment at beginning of the year

VCN – The disbursement rate of public investment from the State budget in 2022 has not reached as expected. This requires ministries, sectors and localities to provide solutions and expedite this work, disburse public investment into projects for projects' economic development.
Outward investment of SOEs sees positive changes

Outward investment of SOEs sees positive changes

VCN - The outward investment of state-owned enterprises (SOEs) is not entirely directly invested by the parent company, but mainly through subsidiaries. In 2021, many outward investment projects of SOEs and enterprises with state capital recorded a surge in revenue and profits year-on-year besides loss-making investment projects. To improve efficiency of investment, the Government will restructure outward investment activities.

Latest News

Saigontex 2023 attracts over 1,300 domestic, foreign businesses

Saigontex 2023 attracts over 1,300 domestic, foreign businesses

More than 1,300 businesses from 21 countries and territories are participating in the Vietnam Textile & Garment Industry Expo (Saigontex) 2023, the leading exhibition of the industry in Southeast Asia, which opened in Ho Chi Minh City on April 5.
Mong Cai international border gate sees strong recovery

Mong Cai international border gate sees strong recovery

The Mong Cai international border gate in the northern province of Quang Ninh has become vibrant as before the pandemic, showing a positive sign in the economic recovery of Mong Cai city in particular and Quang Ninh province in general.
Vietnam a potential market for French businesses, investors: experts

Vietnam a potential market for French businesses, investors: experts

French businesses should innovate their approach, enhance their understanding of culture and language, and make changes to adapt to Vietnam's transitioning economy in order to expand their market share and boost investment in the Southeast Asian nation, said Dr. Jean-Philippe Eglinger, the founder of the Viet Phap Strategies.
Import and export turnover across Cao Bang prospers but still exists difficulties

Import and export turnover across Cao Bang prospers but still exists difficulties

VCN – After China resumes trade, Cao Bang province's import and export activities see remarkable prosperity.

More News

Cashew industry strives to "get on the shelves of world supermarkets"

Cashew industry strives to "get on the shelves of world supermarkets"

VCN - Although holding the number one position in the world in exporting cashew kernels for many years, the position of Vietnam's cashew industry in the world cashew value chain is very small because it mainly exports kernels with preliminary treatment.
HCM City’s industrial production index down 0.9% in Q1

HCM City’s industrial production index down 0.9% in Q1

Ho Chi Minh City’s Index of Industrial Production (IIP) in the first quarter of 2023 declined by 0.9% compared to the same period last year, the municipal Department of Industry and Trade reported at a press conference on April 3.
Fisheries exports estimated at 1.85 billion USD in Q1

Fisheries exports estimated at 1.85 billion USD in Q1

Fisheries export value was estimated at 1.85 billion USD in the first quarter (Q1) of this year, a fall of 27% compared to the same period last year due to lower consumption and import demand under the impacts of inflation and economic recession, according to the Vietnam Association of Seafood Exporters and Producers (VASEP).
Quang Ninh aims to attract quality FDI inflows

Quang Ninh aims to attract quality FDI inflows

The northern coastal province of Quang Ninh has strengthened measures to attract quality foreign direct investment (FDI) inflows, especially from big names in the processing-manufacturing industry.
Exports face many difficulties

Exports face many difficulties

VCN - In the first months of 2023, the absence of export orders plus the downward trend in commodity prices have slowed down trade activities.
Manufacturing enterprises increase their competitiveness thanks to digital transformation

Manufacturing enterprises increase their competitiveness thanks to digital transformation

VCN - Overcoming difficulties in 2023 requires manufacturing enterprises to self-improve and innovate. Digital technology is one of the effective solutions to help manufacturing businesses grow and compete.
32nd Việt Nam Expo promises to boost business linkages

32nd Việt Nam Expo promises to boost business linkages

The 32nd Việt Nam International Exhibition (Vietnam Expo) will take place in Hà Nội from April 5-8 with the participation of more than 500 domestic and foreign enterprieses, the event’s organisers have announced.
Prevention of price risks before news that Indonesia increases rice imports in reserve

Prevention of price risks before news that Indonesia increases rice imports in reserve

VCN - In response to demand signals from key markets such as Indonesia and the Philippines, the Import-Export Department (Ministry of Industry and Trade) suggested that rice exporters actively monitor the market situation and fully assess the opportunities as well as risks to build a trading plan.
Japanese investors highly appreciate Vietnamese property market

Japanese investors highly appreciate Vietnamese property market

Representatives from around 180 Japanese businesses and investors on April 1 attended a Tokyo workshop on Vietnamese real estate, during which many of them highly appreciated the potential of Vietnam’s property market.
Read More

Your care

The system has not recorded your reading habits.

Please Login/Register so that the system can provide articles according to your reading needs.

Latest Most read
Saigontex 2023 attracts over 1,300 domestic, foreign businesses

Saigontex 2023 attracts over 1,300 domestic, foreign businesses

More than 1,300 businesses from 21 countries and territories are participating in the Vietnam Textile & Garment Industry Expo (Saigontex) 2023, the leading exhibition of the industry in Southeast Asia, which opened in Ho Chi Minh City on April 5.
Mong Cai international border gate sees strong recovery

Mong Cai international border gate sees strong recovery

The Mong Cai international border gate in the northern province of Quang Ninh has become vibrant as before the pandemic, showing a positive sign in the economic recovery of Mong Cai city in particular and Quang Ninh province in general.
Vietnam a potential market for French businesses, investors: experts

Vietnam a potential market for French businesses, investors: experts

French businesses should innovate their approach, enhance their understanding of culture and language, and make changes to adapt to Vietnam's transitioning economy in order to expand their market share and boost investment in the Southeast Asian nation, said Dr. Jean-Philippe Eglinger, the founder of the Viet Phap Strategies.
Import and export turnover across Cao Bang prospers but still exists difficulties

Import and export turnover across Cao Bang prospers but still exists difficulties

VCN – After China resumes trade, Cao Bang province's import and export activities see remarkable prosperity.
Cashew industry strives to "get on the shelves of world supermarkets"

Cashew industry strives to "get on the shelves of world supermarkets"

VCN - Looking back to 2022, while the export turnover of the cashew industry reached US $ 3.08 billion, the import turnover of raw cashews consumed US $ 2.678 billion.
Mobile Version