Ministry of Construction gives "ultimatum" on disbursement of public investment

VCN - The Ministry of Construction recently issued a directive on speeding up the implementation and disbursement of the 2021 public investment capital plan, requiring 100% completion of the capital plan assigned by the end of December 31, 2021.
The Ministry of Construction requested to soon complete the final settlement documents of completed bidding packages of the National Assembly Building project. Source: Internet.
The Ministry of Construction requested to soon complete the final settlement documents of completed bidding packages of the National Assembly Building project. Source: Internet.

Disbursement reached 22.2% of the allocated plan

According to the Ministry of Construction, units have made great efforts to accelerate the implementation and disbursement of public investment capital in 2021.

However, implementation is still limited, is not effective, not drastic in some units, the leaders of some units are not thorough, lack urging, inspection and responsibility in the implementation of the project, coordination in handling work and organisation of implementation is still not tight, there is still the situation of passing and avoiding responsibility.

Discipline in public investment is not strict, so some projects are implemented slowly and implementation is not on time; a number of projects have completed volume, but the procedures for acceptance, payment and finalisation are slow, leading to a low disbursement value of the public investment capital plan in 2021, affecting plan implementation from the Ministry of Construction.

Regarding investment projects using public investment capital, the Ministry of Construction said at the beginning of the year, the ministry assigned details of the 2021 State budget capital investment plan (phase 1) for investment projects meeting the conditions with capital of 322.52 billion VND.

The remaining capital (VND 353,719 billion) would be delivered immediately after the National Assembly approves the medium-term public investment plan for 2021-2025. In the first six months of the year, disbursed public investment capital was 70.54 billion dong, reaching 22.2% of the plan.

Implementing the medium-term public investment plan for 2021-2025, the Ministry of Construction has completed a detailed capital allocation plan, finished the appraisal and approved investment policies for projects in the medium-term investment portfolio in 2021-2025 with a total expected capital of VND 3,006.9 billion, which has been submitted to the Ministry of Planning and Investment for appraisal.

For projects using economic public service funds, in 2021, the Ministry of Construction will manage 64 tasks and programmes (including 46 newly opened tasks) with a total budget of 28.83 billion dong.

Regarding ODA projects, in 2021 the Ministry of Construction is directly managing, implementing and coordinating 10 ODA programmes and projects with a total budget of VND 59.93 billion (of which, the counterpart is VND 17.26 billion and foreign capital is VND 42.67 billion).

100% of the 2021 capital plan must be completed by December 31, 2021

To ensure completion of the public investment capital plan assigned in 2021, the Minister of Construction requested heads of the affiliated units to urgently direct the synchronous, drastic and effective implementation of tasks, and solution.

Accordingly, speeding up the preparation of the project, the selection of contractors is in accordance with the law, and early starting the work, as well as conducting online bidding, ensuring publicity and transparency, and selection of qualified contractors.

Remove difficulties and obstacles, ensuring progress of works; expeditiously check and accept, make payment documents as soon as the volume is available, carry out the payment procedures of investment capital for the project within four days from is checked and accepted as prescribed, not to accumulate payments at the end of the year, not to cause outstanding debt for capital construction.

For example, for the construction investment project of the National Assembly House, the Ministry of Construction requested urging contractors and related units to speed up the completion of finalisation documents of completed bidding packages to timely disburse public investment capital in 2021.

Maximise human resources to complete the checking and payment procedures for contractors; complete final settlement documents for bidding packages audited by the State Audit, and submit them to the Ministry of Construction for verification and approval in accordance with regulations; handle problems or promptly report problems beyond their competence to the Ministry of Construction.

The Ministry of Construction also requires 100% of the capital plan assigned 2021 must be completed by the end of December 31, 2021. Investors must commit to the implementation schedule and disbursement of public investment capital in 2021 with the Ministry of Construction on a monthly basis.

By September 30, projects with a disbursement rate of less than 60% of the public investment capital plan assigned in 2021 (except for new construction projects in 2021 awaiting capital allocation after by the Prime Minister approved a medium-term public investment plan for the period of 2021-2025) will have their capital transferred to projects with good disbursement progress and lacking capital. The Ministry of Construction will review responsibility and take disciplinary measures against the head of the investors for the delay in implementation and disbursement.

The ministry also requested investors to focus on directing, inspecting, urging and promptly handling difficulties and problems in the disbursement of public investment capital, especially problems with investment procedures and procedures for checking, payment and the settlement of investment capital; attaching implementation and disbursement progress and project efficiency to the individual responsibility of the head and the person assigned to perform the task, considering them a criterion for assessing the level of work completion in 2021.

Resolutely and promptly handle organisations and individuals that violate and intentionally obstruct, causing difficulties, slow the implementation and disbursement progress of the 2021 public investment capital plan and promptly replace civil servants, public employees and employees being weak or having negative interferences on the performance of investment capital management tasks and in bidding.

For investors who do not meet their committed progress, are late in submitting the settlement report of completed projects, or do not reach 100% of the disbursement plan for public investment capital in 2021, the Ministry of Construction will handle the responsibility of the head of the investor, at the same time consider the transfer of the project investor, resolutely not allocate capital to start new projects, do not allow them to be the investor of other projects. The head of the unit must be subject to a specific disciplinary action and take responsibility fully before the Minister of Construction.

By Hoai Anh/ Binh Minh

Related News

The more delayed the investment disbursement is, the more accumulated the capital expenditure will be

The more delayed the investment disbursement is, the more accumulated the capital expenditure will be

VCN - According to Dr Nguyen Dinh Cung, former director of the Central Institute for Economic Management (CIEM), amid the downtrend of many of Vietnam's economic growth drivers, public investment is still expected to be the main driver for economic growth recovery in 2023.
Public investment to be the foundation for the development of the stock market

Public investment to be the foundation for the development of the stock market

VCN - Effectively implementing public investment is considered one of the most feasible solutions at the moment to support economic recovery and development in 2023, thereby helping to create a foundation for the development of Vietnam's stock market in the long run.
Focal public investment key to effective disbursement: official

Focal public investment key to effective disbursement: official

A key measure to effective public investment disbursement is to promote investment with focuses, with priority given to regional linkage projects to create new socio-economic development spaces for localities, said Minister-Chairman of the Government Office Tran Van Son at a regular Cabinet press conference on March 3.

Latest News

Corporate bonds worth 1.1 billion USD issued in March

Corporate bonds worth 1.1 billion USD issued in March

The corporate bond market is showing signs of recovery with a notable increase in both the number of issuers and the value of issued bonds in March.
Tax revenue is estimated at VND 426,922 billion in the first quarter

Tax revenue is estimated at VND 426,922 billion in the first quarter

VCN - In the first three months of the year, state budget revenue managed by the tax agency was estimated at VND426,922 billion, equaling 31.1% of the ordinance estimate and 104.6% over the same period. Domestic revenue is estimated at VND411,418 billion, equaling 30.9% of the estimate, up 5.3% over the same period in 2022.
Nearly 400 complaints about insurance distribution through banks on Ministry of Finance hotline

Nearly 400 complaints about insurance distribution through banks on Ministry of Finance hotline

VCN - A representative of the Ministry of Finance said that the Ministry had organized a specialized inspection team on insurance distribution through banks for four insurance companies. The team is finalizing inspection conclusions.
Central bank starts huge credit package for social housing projects

Central bank starts huge credit package for social housing projects

Developers of social housing projects buyers of this kind of houses are entitled to benefit from a credit package worth 120 trillion VND (5.1 billion USD) which was started by the State Bank of Vietnam (SBV) earlier this month.

More News

In Q1, State revenue estimated to rise by 1.3%

In Q1, State revenue estimated to rise by 1.3%

VCN - Total state budget expenditure in the first quarter of 2023 is estimated at VND363.4 trillion, equaling 17.5% of the yearly estimate and rising by 7.2% year-on-year.
Consider raising the level of penalties to ensure fairness and transparency in the stock market

Consider raising the level of penalties to ensure fairness and transparency in the stock market

VCN - Mr Pham Hong Son, Vice Chairman of the State Securities Commission, discussed solutions to improve the capacity, improve fairness and transparency of the stock market.
Central bank cuts policy interest rates to spur growth

Central bank cuts policy interest rates to spur growth

The State Bank of Vietnam (SBV) announced it would reduce several policy interest rates from April 3, the second cut within one month, the regulator announced on its website March 31 night.
Ensure policies to attract investment when implementing global minimum tax

Ensure policies to attract investment when implementing global minimum tax

VCN - On the afternoon of March 30, in Hanoi, the Ministry of Finance held a regular press conference in the first quarter of 2023, chaired by Deputy Minister of Finance Nguyen Duc Chi. Many issues related to the tax field were discussed and answered at the conference.
SBV asks to issue revised decree on foreign ownership cap at Vietnamese banks

SBV asks to issue revised decree on foreign ownership cap at Vietnamese banks

The State Bank of Vietnam (SBV) has suggested the Government to issue a revised decree on foreign investors buying shares from Vietnamese credit institutions.
Solutions to attract FDI when implementing the global minimum CIT

Solutions to attract FDI when implementing the global minimum CIT

VCN - On March 29, the Vietnam International Arbitration Center (VIAC) and the Center for International Integration, the Ho Chi Minh City Institute for Development Studies, jointly held a seminar on Global Minimum Corporate Tax – outlook and challenges in attracting foreign investment (FDI) in Ho Chi Minh City.
Effective implementation of tax incentives as driving force for growth in trade turnover between Vietnam and Cuba

Effective implementation of tax incentives as driving force for growth in trade turnover between Vietnam and Cuba

VCN – The promulgation of Vietnam's Decree on Vietnam's special preferential import tariff to implement the Vietnam-Cuba Trade Agreement for 2022-2027 creates a stable and open legal framework, facilitates import and export activities, brings expected great benefits to the business community of the two sides, promote two-way trade turnover and develop Vietnam-Cuba trade relations.
Being many "hot" issues at the general meeting of shareholders of banks

Being many "hot" issues at the general meeting of shareholders of banks

VCN - International Commercial Joint Stock Bank (VIB) will be the first bank to hold a general meeting of shareholders this week, and then April will be the "peak" for banks to deploy.
Bringing the policies on reducing land rent and water surface rent into life

Bringing the policies on reducing land rent and water surface rent into life

VCN - The tax sector is drastically implementing dissemination and support to make the policy of reducing land rent and water surface rent in 2022 fully effective.
Read More

Your care

The system has not recorded your reading habits.

Please Login/Register so that the system can provide articles according to your reading needs.

Latest Most read
Corporate bonds worth 1.1 billion USD issued in March

Corporate bonds worth 1.1 billion USD issued in March

The corporate bond market is showing signs of recovery with a notable increase in both the number of issuers and the value of issued bonds in March.
Tax revenue is estimated at VND 426,922 billion in the first quarter

Tax revenue is estimated at VND 426,922 billion in the first quarter

VCN - In the first three months of the year, state budget revenue managed by the tax agency was estimated at VND426,922 billion, equaling 31.1% of the ordinance estimate and 104.6% over the same period. Domestic revenue is estimated at VND411,418 billion,
Nearly 400 complaints about insurance distribution through banks on Ministry of Finance hotline

Nearly 400 complaints about insurance distribution through banks on Ministry of Finance hotline

VCN - A representative of the Ministry of Finance said that the Ministry had organized a specialized inspection team on insurance distribution through banks for four insurance companies. The team is finalizing inspection conclusions.
Central bank starts huge credit package for social housing projects

Central bank starts huge credit package for social housing projects

Developers of social housing projects buyers of this kind of houses are entitled to benefit from a credit package worth 120 trillion VND (5.1 billion USD) which was started by the State Bank of Vietnam (SBV) earlier this month.
In Q1, State revenue estimated to rise by 1.3%

In Q1, State revenue estimated to rise by 1.3%

VCN - Total state budget expenditure in the first quarter of 2023 is estimated at VND363.4 trillion, equaling 17.5% of the yearly estimate and rising by 7.2% year-on-year.
Mobile Version