Low disbursement rates of pubic investment in most ministries, agencies and localities
The disbursement rate in the first three months of the year was low and lower than early-year period. Photo: Thuy Linh. |
Many reasons curb the disbursement rate
Disbursed capital of the total investment capital plan of the State budget from the beginning of the year to March 31was estimated at more than VND66 trillion or 11.7% of the plan. The disbursed amount under the capital plans from previous years transferred to 2021 was VND5.2 trillion, or 9.43% of the plan and disbursed amount under the 2021 plan was more than VND 60.7 trillion dong, or 11.95% of the plan, reported the Ministry of Finance.
According to the ministry, the three-month disbursement rate is estimated to be low and lower than in the same period in 2020. Foreign capital has not been disbursed (estimated at only 0.66%). So far, most ministries, central agencies and localities have low disbursement rates.
Up to 44 of 50 ministries and 27of 60 localities have disbursement rates of below 10%. Ofwhich, 31 ministries have not yet implemented disbursement. In addition, three ministries and at least 19 localities have disbursement rates of more than15% of the plan such as Thai Binh (43.24%), the Ministry of Public Security (31.62%), BacNinh (30.2%), Hung Yen (28.67%), Thanh Hoa (27.79%) and Ha Nam (27.63%).
The low disbursement rates were due to ministries, central agencies and localities focusing on disbursement of the 2020 capital plan transferred into 2021.
In addition, several major projects had to adjust investment procedures (North-South highway project,) or investors in the first months of the year have beenpreparing some items such as making bidding plans orconstruction plans which take a long time to get paid volume, said the Ministry of Finance.
Another reason to curb the disbursement rate of public investment is site clearance compensation.
The Ministry of Finance said this work was facing many problems with unit price, compensation plan and relocation of utility works. Moreover, some investors are not decisive to urge contractors to carry out construction, leading to stagnation and slow disbursement.
Another reason is projects funded by ODA loans and concessional loans from foreign donors have been seriously affected by the Covid-19 pandemic because most of their activities are associated with foreign factors from the import of machinery and equipment to foreign experts, workers, contractors, consultation and supervision and donors. Disbursement is also delayed due to lack of completed volume.
Capital allocation should not be delayed
The Ministry of Finance also reported on the disbursement rates of some key projects such as the land acquisition, compensation and resettlement project of Long Thanh airport project disbursed VND 673.9 trillion (14.65%) under the capital plan 2021; or the project to build several North-South Expressway sections to the east in 2017-2020, was disbursed more than VND2trillion (or 13.3% of the assigned plan in 2021).
To speed up disbursement of the 2021 plan of the projects, the Ministry of Finance proposedthe Ministry of Planning and Investment review the remaining 2021 planned capital that has not yet allocated of ministries central agencies and localities to report to the Prime Minister for consideration and decision.
The Ministry of Finance also requests ministries and agencies to develop a National Target Programme for 2021-2025 to submit to competent authorities for approval and to propose a capital plan for 2021 to report to competent authorities to allocate capital to localities.
Related News
Ensure policies to attract investment when implementing global minimum tax
10:33 | 02/04/2023 Finance
Solutions to attract FDI when implementing the global minimum CIT
11:38 | 01/04/2023 Finance
In Q1, State revenue estimated to rise by 1.3%
13:28 | 04/04/2023 Finance
Latest News
Corporate bonds worth 1.1 billion USD issued in March
13:55 | 06/04/2023 Finance
Tax revenue is estimated at VND 426,922 billion in the first quarter
09:56 | 06/04/2023 Finance
Nearly 400 complaints about insurance distribution through banks on Ministry of Finance hotline
14:47 | 04/04/2023 Finance
Central bank starts huge credit package for social housing projects
14:42 | 04/04/2023 Finance
More News
Consider raising the level of penalties to ensure fairness and transparency in the stock market
13:27 | 04/04/2023 Finance
Central bank cuts policy interest rates to spur growth
17:43 | 02/04/2023 Finance
SBV asks to issue revised decree on foreign ownership cap at Vietnamese banks
20:30 | 01/04/2023 Finance
Effective implementation of tax incentives as driving force for growth in trade turnover between Vietnam and Cuba
13:43 | 31/03/2023 Finance
Being many "hot" issues at the general meeting of shareholders of banks
09:24 | 30/03/2023 Finance
Bringing the policies on reducing land rent and water surface rent into life
15:41 | 29/03/2023 Finance
The more delayed the investment disbursement is, the more accumulated the capital expenditure will be
10:22 | 29/03/2023 Finance
Ministry of Finance summarizes the 10-year implementation of the Resolution of the 8th meeting of the 11th Central Committee
10:20 | 29/03/2023 Finance
Deputy PM urges hastened procedures for cancelled IDA loans
14:25 | 28/03/2023 Finance
Your care
The system has not recorded your reading habits.
Please Login/Register so that the system can provide articles according to your reading needs.
Corporate bonds worth 1.1 billion USD issued in March
13:55 | 06/04/2023 Finance
Tax revenue is estimated at VND 426,922 billion in the first quarter
09:56 | 06/04/2023 Finance
Nearly 400 complaints about insurance distribution through banks on Ministry of Finance hotline
14:47 | 04/04/2023 Finance
Central bank starts huge credit package for social housing projects
14:42 | 04/04/2023 Finance
In Q1, State revenue estimated to rise by 1.3%
13:28 | 04/04/2023 Finance